top of page

SANITARY SEWER

WEBER RIVER OUTFALL

$3.2 Million- Completed 2010

Installation of 4,300 of 108" RCP sewer in high groundwater at 20' depths next to the Weber River. Included concrete transition structures, creek and canal crossings.

BDO OUTFALL SEWER

$14.2 Million- Completed in 2015

This project included the installation of approximately 12,000 feet of new 48" to 60" RCP sewer outfall piping, a TBM tunneled pipeline under I-15, an inverted siphon of the Willard Canal and construction of a new 46 mgd sewer lift station with (3) 40HP 20" vertical column pumps designed for 11.5 MGD per pump.

500 SOUTH DIVERSION PHASE 1 PIPELINE

$15.3 Million- Completed in 2018

This new dual force main project includes installing 12,000 feet of 22" HDPE in a deep excavation and a 54" Tunneled crossing of the Jordan River with 25-foot deep slide rail shoring pits. The project will include extensive dewatering and utility relocations; pigging, odor control, and energy dissipation vaults, and concrete road restoration

SOUTH JORDAN FORCE MAIN PROJECT

$10.1 Million- Completed in 2010

Construction of two 42-inch (O.D.) HDPE pipelines, approximately 18,000 feet long. Includes two river crossings (open cut) and two road crossings (bored), installing air/vac valve vaults, including sewage air release valves and sewage vacuum breaker valves, also includes 1,800 linear feet of 48-inch HOBAS gravity sewer line and manholes, and the installation of a 4-inch communications conduit with three 1-inch inner ducts along the length of the HDPE pipelines. Restoration of wetlands, golf courses, and the Jordan River Trail was also required.

bottom of page